Da Nang Wind Power Project

PPL specializes in providing oversized and overweight transportation solutions for industrial, energy, infrastructure construction and machinery manufacturing projects. With over 5 years of experience in handling goods with sizes and weights exceeding standard limits, we ensure safety, accuracy and on-time delivery.

f82564eb3235966d1aa852a8b4ca2545fb71ec51

Goals & Scope of Work

  • Transporting super-sized and super-heavy turbine blades (62 m), 135-ton turbine cluster (nacelle) and separate tower (total weight 2,100 tons)
  • Providing 8-axle tractors, hydraulic multi-axle trailers and crawler cranes for loading, unloading and assembling
  • Surveying the route of more than 600 km from Cam Ranh port to the foot of Chu Yang Sin mountain
  • Requesting special circulation permits, coordinating with local authorities

Key Challenges

  1. Super-long size: 62 m long turbine blades, difficult to navigate narrow turns, weak bridges on many sections of the road.
  2. Mountainous terrain: up to 1,200 m high, steep and bumpy roads, requiring continuous safety monitoring.
  3. Complicated administrative procedures: requesting traffic permits, coordinating traffic through 3 provinces (Khanh Hoa - Phu Yen - Dak Lak).
  4. Urgent time: the entire chain must be completed within 60 days to meet the turbine installation schedule.

Solutions & Deployment

  1. Survey & 3D Simulation: Identify narrow points, weak bridges; map the optimal route to avoid sensitive residential areas.
  2. Segmentation plan: Turbine blades are transported in 3-piece clusters, assembled at the foot of the project.
  3. Specialized equipment:
  • 8-axle tractor (200-ton capacity)
  • Hydraulic multi-axle trailer extending to 70 m
  • 300-ton crawler crane for lifting and lowering

Project Overview

Investor

Dak Lak Wind Power Joint Stock Company

Capacity

50 MW (14 turbines, 3.57 MW each turbine)

Location

Ea Sup District, Dak Lak Province

Time of execution

Ea Sup District, Dak Lak Province

Results & Effectiveness

  1. Completed 14 turbines on schedule (60 days)
  2. Zero incident: no safety problems, equipment loss
  3. Saved 12% of cost compared to estimate thanks to route optimization and transportation segmentation
  4. Reduced 20% of procedure time thanks to experience in applying for special circulation permits
background

Customer reviews

Sincere Compliments - PPL's ​​Motivation

container-1 container

Experienced personnel and transport equipment are among the aspects we evaluate very strictly. Up to this point, I find that PPL has done an excellent job in ensuring the safety of oversized and overweight cargo transportation.

image
Investor of the Nhon Trach 3 & 4 Thermal Power Plant Project

I highly appreciate the working spirit and professionalism of PPL. PPL demonstrates great professionalism in providing manpower to ensure the safety and success of the project.

screenshot-2025-09-16-175900
Representative of the HRSG Modules Project PV Shipyard

PPL is a highly reputable transportation provider, with modern equipment that ensures safety and success for the project. Moreover, with reasonable pricing that aligns with the project's budget, we chose PPL.

image-60-removebg-preview-1
Representative of H425 ship project of Austal Vietnam Dong Xuyen Industrial Park

PPL has worked in a very professional manner, especially in terms of transportation vehicles. In addition, PPL’s staff coordinated smoothly with other parties. We are very pleased to have a logistics service provider as professional, responsible, and efficient as PPL.

image
Director of Super Freight Company India
1/4

Notice