TPC Offshore Wind Power Generation Phase II Project (OSS Topside)

On June 21-22, 2025, at PV Shipyard (Vung Tau), PPL successfully transported and launched the nearly 4,000-ton (including launching girders) offshore substation topside, a massive structure manufactured by the main contractor PV Shipyard. This marks the first time in Vietnam that an offshore substation topside component has been entirely planned, transported, and launched by a domestic enterprise – utilizing a self-propelled hydraulic trailer system (SPMT).

This event is not only a milestone for PPL but also signifies a strategic advancement for Vietnam's engineering logistics industry – from dependence on international contractors to the ability to fully master the solutions, means, equipment, and processes for handling oversized and heavy components.

Goals & Scope of Work

  • Conduct site surveys and develop detailed engineering plans.
  • Mobilize, configure, and operate the SPMT system.
  • Transport the topside from the fabrication yard to the launching site.
  • Organize load-out/launching according to international safety standards.
  • Monitor and ensure technical safety throughout the entire deployment process.

Key Challenges

With a load of nearly 4,000 tons (including the launching beams), an extremely complex S-shaped route, limited space, and tight deadlines, absolute safety had to be ensured under changing tidal conditions.

Project Overview

Investor / Partner of PPL

Shinfox Energy (SFE) / Petrovietnam Marine Shipyard

Services Provided:

Site-move, Load-out

Cargo Information:

01 topside

Weight:

4000 tons

Dimensions:

62.763 x 39.249 x 31.255 m