Tuy Hoa Wind Power Project
PPL specializes in providing oversized and overweight transportation solutions for industrial, energy, infrastructure construction and machinery manufacturing projects. With over 5 years of experience in handling goods with sizes and weights exceeding standard limits, we ensure safety, accuracy and on-time delivery.
Goals & Scope of Work
- Transporting super-sized and super-heavy turbine blades (62 m), 135-ton turbine cluster (nacelle) and separate tower (total weight 2,100 tons)
- Providing 8-axle tractors, hydraulic multi-axle trailers and crawler cranes for loading, unloading and assembling
- Surveying the route of more than 600 km from Cam Ranh port to the foot of Chu Yang Sin mountain
- Requesting special circulation permits, coordinating with local authorities
Key Challenges
- Super-long size: 62 m long turbine blades, difficult to navigate narrow turns, weak bridges on many sections of the road.
- Mountainous terrain: up to 1,200 m high, steep and bumpy roads, requiring continuous safety monitoring.
- Complicated administrative procedures: requesting traffic permits, coordinating traffic through 3 provinces (Khanh Hoa - Phu Yen - Dak Lak).
- Urgent time: the entire chain must be completed within 60 days to meet the turbine installation schedule.
Solutions & Deployment
- Survey & 3D Simulation: Identify narrow points, weak bridges; map the optimal route to avoid sensitive residential areas.
- Segmentation plan: Turbine blades are transported in 3-piece clusters, assembled at the foot of the project.
- Specialized equipment:
- 8-axle tractor (200-ton capacity)
- Hydraulic multi-axle trailer extending to 70 m
- 300-ton crawler crane for lifting and lowering
Project Overview
Investor
Dak Lak Wind Power Joint Stock Company
Capacity
50 MW (14 turbines, 3.57 MW each turbine)
Location
Ea Sup District, Dak Lak Province
Time of execution
Ea Sup District, Dak Lak Province
Results & Effectiveness
- Completed 14 turbines on schedule (60 days)
- Zero incident: no safety problems, equipment loss
- Saved 12% of cost compared to estimate thanks to route optimization and transportation segmentation
- Reduced 20% of procedure time thanks to experience in applying for special circulation permits

Customer reviews
Sincere Compliments - PPL's Motivation


1/4