Completed the 2 module loadout project at PV Shipyard

15.03.2022

The project of transporting and launching 2 Kanfa modules at PV Shipyard port was carried out from March 4, 2022 to March 10, 2022 by Bao Tin Trading and Logistics Company Limited (PPL).

Successfully transporting and launching 2 modules at PV Shipyard port in difficult conditions of terrain and obstacles. But with experience in the field of transporting super-heavy goods, PPL has successfully and safely loaded out 2 modules.

To be able to transport and ensure absolute safety for the 2 modules, experts and PPL staff had to plan, carefully plan, calculate the technical parameters and most importantly, monitor the level. water balances the barge with the outside water level at the time of launching the cargo into the barge.

During the implementation of the project, PPL used the SPMT self-propelled hydraulic trailer to bring the modules from the wharf to the barge, arranged in order. The process is smooth, safe and on schedule.

In addition, in order to be able to capture the weather situation, PPL has installed devices to monitor weather developments, the rising and falling tide levels to be able to proactively capture the water level during the process. perform.

Up to now, all loadout stages have been almost completed. PPL ensures the scheduled schedule and ensures absolute safety during the implementation process.

We can see that PPL has been and continues to affirm its position in the field of logistics in general and especially in the field of transporting oversized and super-heavy goods in particular. PPL is currently present, in conjunction with most of its partners in industrial parks and seaports throughout the country.