Kasawari Project

Three oversized and overweight Membrane Skids, each weighing 236 tons and measuring 20m x 11.49m x 7.1m, were transported from the Vina Offshore factory to Dong Xuyen port for launching onto a barge.

sa-lan-1

Goals & Scope of Work

  • Absolutely safe transportation, no scratches on the goods.
  • Completion on schedule: June 1st, 2021 – June 6th, 2021.
  • Arrangement of vehicles, route survey, and safe loading onto barge.

Key Challenges

  1. Extremely large in weight and size (236 tons/package; 20m long).
  2. The route is only 1 km long but has many curves, trees, and power lines.
  3. Strict lifting and transportation technical requirements.
  4. Precise tidal timing must be calculated for load-out.

Solutions & Deployment

  • Study technical drawings and conduct detailed site surveys.
  • Deploy a 24-axle SPMT, forklifts, cranes, and specialized barges.
  • Remove obstacles before transportation.
  • Coordinate transportation according to tidal conditions to ensure safe load-out.
  • Organize dedicated personnel to supervise the entire process.

Project Overview

Project Name

Load-out 3 Skids

Cargo Package

Membrane Skids

Quantity

3 packages

Weight per package

236 tons

Dimensions

20m x 11.49m x 7.1m

Route

Vina Offshore Garment Factory - Dong Xuyen Port

Shipping Time

June 1, 2021 - June 6, 2021

Results & Effectiveness

  • All three shipments were transported on schedule and with absolute safety.
  • Loading onto the barge was successful without incident.
  • This confirms PPL's ​​capabilities in oversized and overweight cargo transportation and has been highly appreciated by the client.