Load out modules on the project barge HRSG Modules

27.12.2021

Modules in the project HRSG Modules - Transporting and launching 4 modules are being implemented in turn by PPL experts
 
The plan to load out the modules onto the barge is carried out by PPL experts with thorough work

  • The trailer goes under the package and proceeds to receive the goods.
  • Pre-ballast pump
  • Conduct lift test so that PVS & DXP can cut the pillows and line the cut pillow to give enough space for the trailer to move.
  • Sitemove position in front of the jetty slope
  • Bridge liners
  • Loadout at 2.3 tide

The team of PPL experts assigned to carry out the project are all people with extensive experience in Load in & Load out projects of partners.

12
Photo: PPL experts implementing HRSG Modules project