Using dedicated equipment SPMT sitemove 4 modules
On December 24, PPL loaded out 4 modules at Dong Xuyen port under the project HRSG Modules - Transport and Launch 4 modules.
To best deploy the transport and launch of 4 modules, PPL planned to use specialized transport vehicles, which are SPMT self-propelled hydraulic trailers. All methods are calculated in detail, accurately and safely by the PPL team before implementation.

In the first category, lasing trailer is used in conjunction with the SPMT hydraulic trailer system to transport the modules with the extra-large mass.

With the super weight of the modules along with the topographical characteristics of each move, the SPMTs will be arranged and linked together in the form of head - end (like train carriages) or arranged in the form of 2 axes, 4 shaft and 8 axes.

SPMT's wheels can be rotated 360 degrees so that the control can be easily moved in different directions without spending too much time and are controlled by professional experts.